Steel structures

Fabrication and erection of structural steel frames, sheds and canopies.

Structural steel work covers fabrication, erection and alignment of frames, sheds and canopies, tied into the civil work already on site.

How the work runs

  1. Bolts before steel

    Holding down bolts are set in a template while the foundation is cast. The accuracy of the whole frame is decided here, weeks before any steel arrives on site.

  2. Erection

    Columns are landed, plumbed and temporarily braced, then rafters lifted and seated. Each bay is closed and braced before the next is started, so the erected part is never relying on the crane.

  3. Bolting up

    Connections are made to the specified torque and marked. Welded joints follow the procedure and are visually inspected, with testing where the drawing calls for it.

  4. Finishing

    Grouting under base plates, touch up of the coating where it was damaged in handling, and the fixing of sheeting and rainwater goods.

What decides whether it goes well

  • Steel is unforgiving of civil work. A base plate 20mm out of position is packed, drilled or cut, and all three are worse than setting it right.
  • Temporary bracing stays until the permanent bracing is in. Most frame failures happen during erection, not in service.
  • Damaged coating is repaired before sheeting goes on, because after that nobody can reach it.

On site

This work on our own jobs.

Photographs from the projects where we did it.

Where we did it

Projects with this scope.

Structural steel erection Completed

Structural steel erection

Fabrication and erection of a structural steel frame.