Fabrication and erection of a structural steel frame.

A structural steel frame fabricated to shop drawings and erected on site: columns landed and plumbed, rafters seated, purlins and bracing fixed, and the connections bolted to torque.

The accuracy of a steel frame is decided weeks before any steel arrives. Holding down bolts are set in a template while the foundation is cast, and a bolt group out of position by 20mm has to be packed, drilled or cut later. All three are worse than setting it right the first time.

Erection proceeds bay by bay. Each column is plumbed and temporarily braced, the rafter is lifted and seated, and that bay is closed and braced before the next is started, so no part of the frame is relying on the crane to stand up. Most steel failures happen during erection rather than in service, and that is why the temporary bracing stays until the permanent bracing is in.

Base plates are grouted, coating damaged in handling is made good before sheeting goes on, and every bolted connection is marked once it has been tightened to its figure.