Civil and RCC

Slab and deck reinforcement

Completed

Shuttering, reinforcement and concrete pour for slab and deck work.

Deck and slab work: shuttering laid and levelled, reinforcement cut, bent and tied to the bar bending schedule, and the concrete placed, vibrated and cured.

The reinforcement is set out in two mats with chairs holding the top steel at its designed height. Laps are staggered rather than lined up in one plane, because a row of laps at the same section is a weak line across the slab. Cover blocks go in at spacing before the pour, not thrown in as the concrete arrives.

A pour is planned backwards from the construction joint. Concrete is placed continuously to that joint, vibrated enough to release the air but not so long that the mix segregates, then finished and covered for curing. Curing is the part that gets skipped when the programme is tight, and it is the part that turns the mix into the strength the design assumed.

Cubes are cast from the same pour and marked at the time. A cube taken from a later batch certifies that batch and nothing else.